Projects / MTPD District II Substation and Training Facility
MTPD District II Substation and Training Facility
Duration: 2012–2016
Owner: WMATA
Cost: $30 Million
(EPCM, Inc. part of Clark/Baker Design Build team 2012-2016)
EPCM, Inc. responsible for design and construction period services for the entire project for electrical/communication of Police Station and Firing Range, coordination with Utility companies for power, telephone and cable service. Responsibilities includes design of Power, Lighting, site lighting, Fire Alarm, Security System, access control system and Communication System. Responsibilities also included construction period services.